Project Overview Sewer System Improvements

Project will consist of rehabilitating defects in the sanitary sewer collection system that are identified in the FY22 sanitary sewer evaluation survey (SSES) Project. Potential rehabilitation efforts will include cured-in-place pipe (CIPP) lining, manhole rehabilitation and miscellaneous point repairs. The project is part of the City of Auburn's <a href="">Other</a>.

Status

  1. Design
  2. Bid Advertisement
  3. Contracts
  4. Construction

Lining of the sewer main beneath Jordan Hare Stadium began 12/27/2024 and was completed on 12/30/2024. All work on the Auburn University campus, other than punchlist items, has been completed. Contractor mobilized to the Willow Creek area in early February and has begun manhole lining work. ​Project is expected to be completed in March 2025.